Ernest Rutherford Building Artesian Resilience - Contractor

This tender is using the new split file responses feature on GETS. The agency has indicated that they would like to receive responses separated by price and non price components. Please keep this in mind when preparing your response for submission via GETS.

Details

RFx ID : 32630934
Tender Name : Ernest Rutherford Building Artesian Resilience - Contractor
Reference # : 25-376
Open Date : Tuesday, 30 September 2025 6:00 AM (Pacific/Auckland UTC+13:00)
Close Date  : Friday, 24 October 2025 10:00 AM (Pacific/Auckland UTC+13:00)
Department/Business Unit : People, Culture & Campus
Tender Type : Request for Proposals (RFP)
Tender Coverage : Sole Agency  [?]
Categories :
  • 22000000 - Building and Construction Machinery and Accessories
  • 72000000 - Building and Facility Construction and Maintenance Services
Regions:
  • Canterbury
Exemption Reason : None
Required Pre-qualifications : None
Contact : Jacqui Kingi
03 3693209
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Overview

This procurement relates to the construction and installation of resilience upgrades for the artesian cooling system in the Ernest Rutherford building.

The Ernest Rutherford building houses specialised research laboratories and equipment that are dependent on a continuous artesian cooling system. At present there is no redundancy; the building relies on a single pump located above the artesian well. If that pump fails, cooling to critical laboratory equipment ceases immediately. The consequence of such a failure would be catastrophic with disruption to research, significant financial loss through damaged equipment, and reputational damage to the University.

The scope of works includes three zones and will be delivered by a single package of works by one contractor:

• Zone 1: Lobby Artesian Well – Construct a new wall to encapsulate the artesian well manhole within the plant room, relocate services, and install new mechanical plant, pipework, ductwork, and controls.
• Zone 2: Ground Hydraulics Plant Room – Construct a new concrete plinth, supply and install new mechanical plant with associated pipework, ductwork, and controls.
• Zone 3: Level 6 Plant Room – Construct two concrete plinths, refurbish and relocate the heat exchanger, and provide new mechanical plant, pipework, ductwork, and controls.