Tender Closed
|
|
RFx ID : | 32059642 |
Tender Name : | Hillmorton High School - Science Block - PM Services |
Reference # : |
MOE30104
![]() |
Open Date : | Monday, 14 July 2025 4:00 PM (Pacific/Auckland UTC+12:00) |
Close Date : | Friday, 8 August 2025 5:00 PM (Pacific/Auckland UTC+12:00) |
Department/Business Unit : | Ministry of Education - Approval from Ministry Employee - ie. Case Manager |
Tender Type : | Request for Proposals (RFP) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
All enquires to be made through the GETS Question & Answer function |
Alternate Physical Delivery Address : | All communication is to be directed through GETS |
Alternate Physical Fax Number : | |
Agency Address : | NEW ZEALAND |
The Project background is:
i. This would be the 3rd redevelopment project that the Ministry has planned for Hillmorton School.
ii. The 1st project was the construction of a two- storey Middle School building of 22 Teaching spaces.
iii. The 2nd project was the construction of a new Gym with 3 TS.
iv. Due to Hillmorton School build roll has increased, the Ministry intention is to construct a new Science building on the edge of the North Sports field.
v. The building consists of a two-storey building of 8 science labs and 2 GL with a total area of 1610m2
vi. The Project scope includes all related infra structural services which involves the construction of a storm water detention swale and an underground wastewater pump station and related civil work.
vii. The design has been completed by Baldasso Cortese Noordanus as a lead design, Powell Fenwick for civil and Beca as a sub consultant for the remaining services.
viii. The Procurement for main contractor is based on a traditional procurement process of using four main contractors from the Ministry Panel.
The detailed design has now been completed and is currently being reviewed and Project QS is currently doing a detailed design estimate of the cost.
ix. Ministry Investment Board is currently in the process of approving the Business case submitted for this project.
x. A duration of 12 month is expected for construction
This tender has been awarded.