Tender Closed
|
|
RFx ID : | 27831973 |
Tender Name : | Kuranui College - Blk E Upper Level Decramastic Roof Replacement (Wairarapa) |
Reference # : | |
Open Date : | Friday, 11 August 2023 9:00 AM (Pacific/Auckland UTC+12:00) |
Close Date : | Wednesday, 6 September 2023 5:00 PM (Pacific/Auckland UTC+12:00) |
Department/Business Unit : | Board of Trustees - Approve by BoT - ie. School Principal |
Tender Type : | Request for Tenders (RFT) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
All submissions to be made through the GETS website |
Alternate Physical Delivery Address : | All submissions to be made through the GETS website |
Alternate Physical Fax Number : | |
Agency Address : | NEW ZEALAND |
The BOT at Kuranui College are seeking the services of a main roofing contractor to undertake the Blk E Upper Level Decramastic Roof Replacement project. The work is described in the tender documents prepared by IR Group and involves:
• Fencing off the proposed site area and maintaining escape routes to all fire exits. Isolate work areas and operate under SSSP
• Remove and dispose of existing decramastic tiling. Full upper level roof replacement in corrugate iron 0.55
• Replace associated flashings, spouting and downpipes where necessary. Replace rotten rafters, purlins and barge boards where necessary.
• Purlins may need to be installed at 900 centers based on layout of existing roofing underlay. Purlins can be fixed to the existing battens which support the existing roof.
• Tenderer MUST allow for 2x saddle flashings where the 3x roof ridges junction. Saddle flashings must be powder coated, welded aluminium. These must also be tight fitting, riveted and sealed.
• Appropriate use of all associated edge protection, scaffolding and H&S requirements. Leave site clean and tidy.
The project will be a complete turnkey project where the completed section of the building ready for school use will be handed over on completion.
Project consultants are:
o Project Manager: IR Group
o Lead Designer: N/A
Contractors are expected in their tender responses to demonstrate how they will ensure an efficient and prompt delivery by pre-order products and lining up sub-contractors to ensure disruption to the school and construction time is minimised.
The Contractor will be engaged through an MOE medium works contract (Construction contracts for professional services and works).
When responding, please ensure you complete:
- Form of Tender Part A
- Form of Tender Part B
This tender has been awarded.