Tender Closed
|
|
RFx ID : | 25210621 |
Tender Name : | Main Building Contractor for Administration Area at Oamaru Intermediate School |
Reference # : | |
Open Date : | Thursday, 9 December 2021 9:00 AM (Pacific/Auckland UTC+13:00) |
Close Date : | Tuesday, 25 January 2022 3:00 PM (Pacific/Auckland UTC+13:00) |
Department/Business Unit : | Board of Trustees - Approve by BoT - ie. School Principal |
Tender Type : | Request for Tenders (RFT) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
All enquiries to be made through the GETS Questions & Answer function. |
Alternate Physical Delivery Address : | All submissions to be made through the GETS website. |
Alternate Physical Fax Number : |
This Registration of Interest is for the Main Building Contractor to undertake the proposed Administration Area alterations and additions (first stage), which incorporates two Learning Support Co-Ordinators Offices
Project consultants are:
o Project Manager: Michael Forgie of Forgie Hollows & Associates (Oamaru) Ltd
o Designer: Ian Perry of i.design, Oamaru
o Engineer: Richards Consulting Engineers, Christchurch
o Quantity Surveyor: Michael Forgie of Forgie Hollows & Associates (Oamaru) Ltd
The Contract Works required are:
o The proposed alterations additions and refurbishment of the Oamaru Intermediate School’s Administration Area, led by a Main Building Contractor, who would engage numerous subcontractors (roofing; aluminium joinery; joinery; electrical services; plumbing and drainage; stopping; painting; and floor and wall coverings).
o The proposed contract works are deemed medium size
o The works are to the School’s existing Administration Area and involve the first stage of a major alteration, additions and refurbishment of these spaces, which will necessitate the temporary relocation of the School’s Administration Area throughout the duration of the Contract Works.
o The Contractor will be engaged through a Medium Works Contract. No Contract related tags will be considered. The Principal prefers there to be no drawings and specification related Tags.