Tender Closed
|
|
RFx ID : | 23364658 |
Tender Name : | Main Construction Contractor for Refurbishment of 5 classrooms and associates spaces at Westbrook School |
Reference # : | 212190 |
Open Date : | Thursday, 1 October 2020 9:00 AM (Pacific/Auckland UTC+13:00) |
Close Date : | Wednesday, 28 October 2020 3:00 PM (Pacific/Auckland UTC+13:00) |
Department/Business Unit : | Board of Trustees - Approve by BoT - ie. School Principal |
Tender Type : | Request for Tenders (RFT) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
All enquires to be made through the GETS website |
Alternate Physical Delivery Address : | All submissions to be made through the GETS website |
Alternate Physical Fax Number : | N/A |
Agency Address : | NEW ZEALAND |
Westbrook School is a year 0-6 primary school in Pomare, Rotorua.
The school is completing their second ILE modification to relocatable buildings.
The school's Board of Trustees wish to engage a suitable main contractor to undertake this 5YA and SIP project.
The works are in separable portions with the 5 classrooms being the first portion. The remaining portions are decking and exterior door to an adjoining block, timber screen infills, replacement windows to double glazing. There is one provisional sum item.
Block K (Rooms 15 and 16)
• Asbestos cladding removal
• Remove the existing sinks and benches.
• Change the existing lobby area and resource room to wet area and breakout space.
• Bag storage to be moved onto the new covered decks.
• Relocate the server.
• New doors and windows onto the new covered decks.
• End of life replacement of heating, floor and wall coverings, insulation.
• Additional lighting installed.
• New whiteboards/storage units.
Block N (Room 17)
• Remove the existing sink and bench.
• Remove the walls to the resource room.
• Bag storage to be moved onto the new covered decks.
• New doors and windows onto the new covered decks.
• End of life replacement of heating, floor and wall coverings, insulation.
• Additional lighting installed.
• New whiteboards/storage units.
Block N (Toilets)
• Remove the existing basins and 1 x pan from girls’ toilet and 2 x urinals from boys’ toilet
• Change the existing lobby area to a wet area
• Install basins in new location
Block N (Infill area 28.53m2)
• Remove existing built up gardens
• Create 2 x new breakout spaces
Block M (Rooms 18 and 19)
• Remove the existing sinks and benches.
• Change the existing lobby area and resource room to wet area and breakout space.
• Bag storage to be moved onto the new covered decks.
• New doors and windows onto the new covered decks.
• End of life replacement of heating, floor and wall coverings, insulation.
• Additional lighting installed.
• New whiteboards/storage units.
This tender has been awarded.