Tender Closed
|
|
RFx ID : | 21900199 |
Tender Name : | Main Building Contractor for the Construction of Alterations and Additions to Blocks A, G, H, and I at Wainui Beach School |
Reference # : | 1860 |
Open Date : | Friday, 8 November 2019 9:00 AM (Pacific/Auckland UTC+13:00) |
Close Date : | Thursday, 5 December 2019 5:00 PM (Pacific/Auckland UTC+13:00) |
Department/Business Unit : | Board of Trustees - Approve by BoT - ie. School Principal |
Tender Type : | Request for Tenders (RFT) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
Adam Gatley 06 8679622 |
Alternate Physical Delivery Address : | All responses must be uploaded on GETS |
Alternate Physical Fax Number : | N/A |
Agency Address : | NEW ZEALAND |
The Contract Works required are:
i. Block A - Replace gable ends soffits, barges and apron flashing East side. Paint.
ii. Block G - Replace external cracked cement sheet cladding. Replace flashings on
the gable ends where the lean-to roofs hit the high walls of the main building.
iii. Block G - Replace internal water damaged (leaks now fixed) linings in lobby and
toilets. Replace with new particle board to match existing undamaged linings.
Replace also water damaged pinex ceiling linings in the toilets.
iv. Block H - Replace external Shadowclad cladding South and East sides. An
allowance is included for some wall framing replacement and also replacement of
the aluminium windows on the south side. Replace with new H3.2 CCA Shadowclad
and H3.2 battens, fixed with s/steel nails on cavity battens over building wrap. Any
replacement framing to be H3.1 SG8 radiata pine. New APL Metro or Fletcher
Pacific Architectural windows (casement or top hung only). 0.55mm Colorsteel Maxx
flashings.
v. Block H - Replace deck and ramp timber with new H3.2 pine decking.
vi. Block I - Replace external Shadowclad cladding - 50% of external walls allowed for.
An allowance is included for some wall framing replacement and also replacement
of the aluminium windows on the south side. Replace with new H3.2 CCA
Shadowclad and H3.2 battens, fixed with s/steel nails on cavity battens over
building wrap. Any replacement framing to be H3.1 SG8 radiata pine. New APL
Metro or Fletcher Pacific Architectural windows (casement or top hung only).
0.55mm Colorsteel Maxx flashings.
vii. Pool - Replace broken cement sheet (ACM). Replace with James Hardie Titan
board, s/steel nails, paint finished.
viii. A,H,I:Replace all fluorescent lights with new LED batten lights - similar in look all in
same locations as existing lights. Reduced power requirements means there will be
no issue with circuit loading. All fittings to be supplied with Certificates of conformity.
ix. Block A AMS project: Demolish toilets and cloak bay closest to Admin (East) end of
block A. Convert into Break out spaces between classrooms 1 and 2. Raise floor,
carpet, install glass sliding partitions and acoustic rated walls. New ceiling, new
lighting, new acoustic panels, new wet bench work area. Open up solid wall
between classrooms 2 and 3 (middle classrooms) and install sliding glass partition
doors. Possible partial block structural strengthening as pre 1965 building.
x. Remedial work to damaged retaining wall west of Block A.
This tender has been awarded.