Contract No. 138 Ngarue Road Bridge Replacement 2016/17 - Bridge No#17

Details

Tender Closed
RFx ID : 18204900
Tender Name : Contract No. 138 Ngarue Road Bridge Replacement 2016/17 - Bridge No#17
Reference # : C4/302
Open Date : Monday, 5 December 2016 4:00 PM (Pacific/Auckland UTC+13:00)
Close Date  : Tuesday, 20 December 2016 4:00 PM (Pacific/Auckland UTC+13:00)
Tender Type : Request for Tenders (RFT)
Tender Coverage : Sole Agency  [?]
Categories :
  • 72141000 - Highway and road construction services
Regions:
  • Bay of Plenty
  • Gisborne
  • Waikato
Exemption Reason : None
Required Pre-qualifications : None
Contact : Rex Humpherson
rex.humpherson@opus.co.nz
0272356595
Alternate Physical Delivery Address  : Opotiki District Council Administration Office, 108 St John Street, OPOTIKI
Alternate Physical Fax Number  :
Overview

Tenders are invited from suitably qualified contractors for the works described in this document. Briefly, this consists of
demolition and removal of the Te Rereauira Stream Bridge, and replacing it with new box culverts. The works include but are
not limited to foundation preparation, large box culvert installation, backfilling and compaction, pavement construction, road
surfacing and salvaging existing bridge deck. The works are located on Ngarue Rd, Whangaparoa.
The works are outlined on the drawings appended to the contract documents and generally comprise of the following activities:
• Construct of temporary milk tanker access
• Salvaging the existing timber deck and beams and transporting it to ODC storage yard.
• Earthworks
• Installation of new 4 x 2 Box Culvert
• Pavement preparation and construction
• Rehabilitating disturbed areas.
In addition to the above the contract works include:
• Preparing, implementing and managing the Contract Quality Plan according to the Project Specification, Section
4
• General requirements, programming and reporting according to Project Specification, Sections 2 and 3.
• Site safety, traffic management and environmental compliance activities according to Project Specification,
Sections 5, 6 and 7