You are not logged in.

Bridge 181 Main North Line (MNL)

This tender is using the new split file responses feature on GETS. The agency has indicated that they would like to receive responses separated by price and non price components. Please keep this in mind when preparing your response for submission via GETS.

Details

Tender Closed
RFx ID : 32836131
Tender Name : Bridge 181 Main North Line (MNL)
Reference # : 2025/121 Restricted Tender
Open Date : Wednesday, 22 October 2025 9:00 AM (Pacific/Auckland UTC+13:00)
Close Date  : Friday, 19 December 2025 5:00 PM (Pacific/Auckland UTC+13:00)
Tender Type : Request for Tenders (RFT)
Tender Coverage : Sole Agency  [?]
Categories :
  • 22000000 - Building and Construction Machinery and Accessories
  • 30000000 - Structures and Building and Construction and Manufacturing Components and Supplies
Regions:
  • New Zealand
Exemption Reason : 9. Secondary procurement
Required Pre-qualifications : None
Contact : Tuan Nguyen
tuan.nguyen@kiwirail.co.nz
Alternate Physical Delivery Address  : XXX
Alternate Physical Fax Number  :
Agency Address :
Overview

KiwiRail Holdings Limited ("KiwiRail") invites pre-selected parties to submit their tenders ("RFT Response") for the supply of physical works for the Bridge 181 MNL Piers Replacement project ("the Goods/Services").
This RFT is issued by KiwiRail’s Infrastructure – Project Delivery Team to engage a suitably qualified and experienced contractor to carry out the replacement of piers 1 through 5 on Bridge 181, located at kilometrage 329.906 on the Main North Line (MNL) in Blenheim, South Island.
Bridge 181 MNL is a single-track, seven-span, simply supported riveted steel girder bridge on timber pier foundations, crossing the Tuamarina River A. The bridge, constructed in 1962, is 51 metres long and comprises seven steel spans supported by eight piers of hardwood piles. It is situated approximately 10 km north of Blenheim, Marlborough, near State Highway 2.
The timber piers have deteriorated significantly and now require replacement. Although some steelwork strengthening has been completed over the past decade, it has not addressed the degradation of the timber piers.
Due to the condition of the piers, the normal line speed of 90 km/h has been reduced to a Temporary Speed Restriction (TSR) of 25 km/h, which was reviewed and increased to 40 km/h in August 2025.
The objective of this project is to replace the principal load-bearing elements (PLBE) of Bridge 181 MNL. This includes the full replacement of the timber pier foundations with new steel and/or concrete foundation systems.
Please refer to the attached RFT documents for detailed specifications and requirements.

RFx Outcome

This tender has been awarded.

  • Isaac Construction Limited - McArthurs Road, Christchurch, 8051, NEW ZEALAND
    Value $ 1,428,636

Award Date: Wednesday, 3 June 2026 (Pacific/Auckland UTC+12:00)
Date RFx was completed/updated: Wednesday, 3 June 2026 10:15 AM (Pacific/Auckland UTC+12:00)