Tender Closed
|
|
RFx ID : | 22394162 |
Tender Name : | Wastewater Pipeline Rehabilitation |
Reference # : | 20-044 |
Open Date : | Tuesday, 3 March 2020 2:30 PM (Pacific/Auckland UTC+13:00) |
Close Date : | Friday, 20 March 2020 3:00 PM (Pacific/Auckland UTC+13:00) |
Tender Type : | Request for Tenders (RFT) |
Tender Coverage : | Sole Agency [?] |
Categories : |
|
Regions: |
|
Exemption Reason : | None |
Required Pre-qualifications : | None |
Contact : |
Glenn Cooper glenn.cooper@whakatane.govt.nz 07 306 0500 |
Alternate Physical Delivery Address : | tenderbox@whakatane.govt.nz |
Alternate Physical Fax Number : | |
Agency Address : |
The project consists of rehabilitation by trenchless methods of approximately 1225m of the 150mm diameter reinforced concrete, earthenware and Asbestos cement wastewater pipes located in Whakatāne and Murupara townships. The project includes the full scope of work, including pipe cleaning jet-cleaning, and pre and post CCTV inspections of the work undertaken.
The Contractor shall refurbish the pipelines by insertion of a suitable liner. The lateral connections shall also be refurbished by replacement with factory formed wye fittings or with suitable lateral junction repair systems involving proprietary liners extending from the main pipeline to about 1m up the lateral pipe.
The following list of activities is provided as clarification of those activities that are the responsibility of the Contractor:
Set-out
Services location in the vicinity of proposed excavations (if required) and liaison as necessary with utility services providers.
Liaising with, and/or notifying property owners regarding the work if they are to be impacted
Corridor Access Request, work safety plans and traffic management plans as appropriate for each site
Underground pipe location such as using CCTV in conjunction with above-ground tracking devices to locate required excavation sites (if required)
Supply of pipeline, manhole and other incidental materials required to complete the works
Flow control and diversion as required to maintain flow around the section of pipeline affected by the works
Complete works Quality Assurance forms as appropriate
Post construction CCTV of repaired and constructed pipelines
Any other activities required in terms of the General Conditions of Contract.
The contractor is required to confirm the location of all manholes. Those that cannot be accessed or opened should be brought to the attention of the Client who will then attempt to make that manhole accessible. When buried manholes are located, the contractor is required to mark the position of the manhole on the ground surface. The manhole will be raised by others.
This tender has been awarded.