Sir Neil Waters (SNW) Building Extension - Structural Steel Suppliers and Contractors

Details

Tender Closed
RFx ID : 19519333
Tender Name : Sir Neil Waters (SNW) Building Extension - Structural Steel Suppliers and Contractors
Reference # : TB17-35
Open Date : Thursday, 8 March 2018 1:30 PM (Pacific/Auckland UTC+13:00)
Close Date  : Tuesday, 17 April 2018 2:00 PM (Pacific/Auckland UTC+12:00)
Department/Business Unit : Facilities Management
Tender Type : Request for Proposals (RFP)
Tender Coverage : Sole Agency  [?]
Categories :
  • 30000000 - Structures and Building and Construction and Manufacturing Components and Supplies
  • 31000000 - Manufacturing Components and Supplies
  • 72000000 - Building and Facility Construction and Maintenance Services
  • 95120000 - Permanent buildings and structures
Regions:
  • New Zealand
Exemption Reason : None
Required Pre-qualifications : None
Contact : Sonja Ensink
sourcing@massey.ac.nz
06 356 9099
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Agency Address : NEW ZEALAND
Overview

This RFP relates to the purchase, fabrication and erection of structural steel for the Sir Neil Waters building. The key outcomes that we want to achieve are:

- A well-structured Contract Agreement that leads to a win / win outcome for both the University and various providers.

- The seamless novation of this Supplier/ Contractor, prior to the start of construction on site, from the Principal to the Prime Contractor based on terms and conditions acceptable to all parties.

- Full compliance during all stages of the project with the Health and Safety at Work Act of 2015. This Supplier / Subcontractor, as a precondition, needs to confirm that they will accept and comply with any specific Preliminary and
General and / or Safety requirement of the selected Prime Contractor as part of the novation process.

- Secure the materials and fabrication of structural steel prior to the completion of or during the RFP process for a Prime Contractor to ensure programme requirement are met once a Prime Contractor is selected.

- Completion on or under budget, on or ahead of time with zero defects to specified quality objectives and standards including the provision progressively of all required certifications and testing results.

RFx Outcome

No Winner Responses did not meet requirements