Hill Road Reconstruction - Stage 4 Contract AD16-4374

Details

Tender Closed
RFx ID : 21378536
Tender Name : Hill Road Reconstruction - Stage 4 Contract AD16-4374
Reference # : AD16-4374
Open Date : Wednesday, 7 August 2019 4:00 PM (Pacific/Auckland UTC+12:00)
Close Date  : Wednesday, 28 August 2019 4:00 PM (Pacific/Auckland UTC+12:00)
Tender Type : Request for Tenders (RFT)
Tender Coverage : All of Government  [?]
Categories :
  • 30102800 - Piling
  • 30102900 - Post
  • 30103100 - Rails
  • 30111500 - Concrete and mortars
  • 30111600 - Cement and lime
  • 30111800 - Aggregates
  • 30111900 - Concrete reinforcement hardware
  • 30120000 - Roads and landscape
Regions:
  • Wellington
Exemption Reason : None
Required Pre-qualifications : None
Contact : Curtis Lee
curtis.lee@ghd.com
04 474 7327
Alternate Physical Delivery Address  :
Alternate Physical Fax Number  :
Overview

This Contract is for the upgrading of a section of Hill Road in Belmont, Lower Hutt. The existing road layout is of a typical 2 lane 2 way hill road as found on the western hills of the Hutt Valley and doesn’t currently include any formal pedestrian footpath facility. The new layout will be that of a formalised and consistent wider road, with a dedicated pedestrian footpath and improved drainage.

Work will involve site clearing, excavations, a retaining wall, new pavement, kerb and channel, storm water drainage, carriageway surfacing, footpath construction and associated works.

The chip seal surface section of the pavement is to be resealed approx. 12 months after completion of the works as Separable Portion B, with resealing undertaken between the months of November & February.

At the time of tender the pavement design is still to be finalised pending further site testing. In terms of the specified surfacing, no alternative product to the specified SMA (Stone Mastic Asphalt), will be accepted.

The Principal (Hutt City Council) has a quality driven approach to its construction projects. In keeping with this philosophy, Contractors are expected to achieve the highest standard of performance on all aspects of this project. Testing shall be carried out to ensure that quality standards and specification requirements are achieved.

Professional Services Project Management for this Contract is being provided by GHD Limited on behalf of Hutt City Council.